During commissioning

Pay attention to the following points during commissioning:

Check function and adjustment of attachments
Observe information for environment and operation
Check protective measures against moving and live parts

Configuration

Beckhoff recommends the use of the latest TwinCAT version and the TwinCAT Drive Manager 2 for the configuration of new projects.

Create a new TwinCAT project and select the target system
Add modules to the I/O devices via the Scan function
Create a TwinCAT Drive Manager 2 project
Scan components or manually insert a configuration
Configure components inserted in the I/O devices
Check the state and activate TwinCAT