X07 - AX5140

X07 - AX5140 1:

Terminal point

Signal

PE

 

Protective earth

+RB

 

External braking resistor +

+RBint

 

Internal braking resistor +

-RB

 

Braking resistor GND

X07 - AX5140 2:

Commissioning the AX5140

Commissioning the AX5140 can only be carried out when the "+RBint" and "+RB" terminal points are bridged (delivered state) or an external braking resistor is connected ("+RB" and "-RB" terminal points). If these measures are not taken then the AX5140 will be stopped with the error message "FD4B – undervoltage".